Scheduling items

To schedule a planner item, select the Set schedule checkbox or click the Set schedule link.

 

Fig. 57. Creating a scheduled item

Then specify the schedule parameters.

 

Fig. 58. Editing a planner item schedule

On the General tab, specify the schedule end date and time (at the End by field), the number of occurrences (in the Occurrences field), and the schedule period in days, months, and years (Repeat every).

You can check the resulting schedule in the lower part of the window.

One the Weekly tab, specify the weekly schedule:

 

Fig. 59. Editing a weekly schedule of a planner item

In the Repeat every field, specify the schedule period in weeks.

In the Days of the week group, select the days of the week.

One the Monthly tab, specify the monthly schedule:

 

Fig. 60. Editing a monthly schedule of a planner item

In the Repeat on the field, specify the day of the month and/or day of the week, and also specify how it is counted (from the beginning or from the end of the month).

In the Months group, select the months.

You can check the resulting schedule in the lower part of the window.

 

Fig. 61. Description of the resulting schedule

Next page: Deleting items

Be the first to know tips & tricks on business application development!

A confirmation e-mail has been sent to the e-mail address you provided .

Click the link in the e-mail to confirm and activate the subscription.